Sagamore Bridge

MassDOT Files State Environmental Review Document for Cape Cod Bridges Project

DEIR Open House Scheduled for Thursday, September 25, 2025, in Bourne

Healey-Driscoll Administration Also Includes Additional Road Safety Improvements, Extension of Local Bicycle-Pedestrian Path

The Massachusetts Department of Transportation (MassDOT) has filed the Draft Environmental Impact Report (DEIR) for the replacement of the Cape Cod Bridges with the Massachusetts Environmental Policy Act (MEPA) Office. The filing of this comprehensive document represents a significant milestone in advancing the Cape Cod Bridges Project.

The DEIR includes the Healey-Driscoll Administration’s proposed decision to extend construction of Sandwich Road safety improvements—adding a shared-use path to the Gallo Ice Arena—in response to requests from Bourne residents and local officials. The future path will now extend further along Sandwich Road, creating a safe travel option for bicyclists and pedestrians from the Upper Cape Cod Technical High School to the Gallo Ice Arena.

Public Review and Comment

The DEIR will be available for public review in the September 10 edition of the Environmental Monitor. MassDOT has requested an extension of the public comment period from 30 to 44 days to ensure sufficient time for public input.

  • Public Comment Period Ends: October 24, 2025
  • MEPA Certificate Expected: October 31, 2025

How to Submit Comments:

Please reference EEA# 16695 in all correspondence.

DEIR Open House

  • Date: Thursday, September 25, 2025
  • Time: 3:00 – 7:00 PM
  • Location: Bourne Veteran’s Memorial Community Center

Next Steps in the Environmental Review

While the original plan was to file a joint state and federal environmental document, MassDOT has opted for a phased approach.

  • State Review: Filing the DEIR first under MEPA.
  • Federal Review: Filing the Draft Environmental Impact Statement (DEIS) under the National Environmental Policy Act (NEPA) later in 2025.

The Federal Highway Administration (FHWA) anticipates publishing the Notice of Availability of the DEIS in the Federal Register in late summer/early fall 2025, initiating a 45-day public comment period. FHWA and MassDOT will host at least one public meeting on the DEIS, with details provided two weeks in advance.