The Dredge Report | Week of March 28, 2021
Sand Shifter – Stage Harbor, Chatham Earlier in the week, the Sand Shifter finished the main part of the dredging and ‘broke’ through the southeastern edge of the channel and mid-day […]
Read MoreSand Shifter – Stage Harbor, Chatham Earlier in the week, the Sand Shifter finished the main part of the dredging and ‘broke’ through the southeastern edge of the channel and mid-day […]
Read MoreSand Shifter – Stage Harbor, Chatham Nearing the end of this project, last week we were able to dredge three out of six days with dredging operations having to stop […]
Read MoreSand Shifter – Stage Harbor, Chatham Dredging continued from Sunday through Wednesday morning when at low tide a break was found in the pipe. The picture below shows the break […]
Read MoreSand Shifter – Stage Harbor, Chatham Another challenging week with the strong Northerly winds and cold temperatures halting operations on Monday afternoon through Wednesday, resuming dredging on Thursday, stopping again […]
Read MoreSand Shifter – Stage Harbor, Chatham Another challenging week in Stage Harbor, with strong Southerly winds halting operations on Monday, resuming dredging on Tuesday & Wednesday, stopped again on Thursday […]
Read MoreSand Shifter – Stage Harbor, Chatham Dredging continued on Monday, but on Tuesday we had to stop due to the strong northerly winds & seas that lasted throughout the day […]
Read MoreSand Shifter – Stage Harbor, Chatham The Sand Shifter started dredging the Stage Harbor channel on Saturday! Most of the week was spent in mobilizing the pipe, bringing the dredge […]
Read MoreSand Shifter – Stage Harbor, Chatham Another week of putting the many pieces of the Stage Harbor ‘jig saw’ puzzle together continues! What’s left until we can actually start dredging? […]
Read MoreCod Fish II – Sesuit Harbor, Dennis Dredging took place just two days last week. The weather on Monday still had seas to high keeping the Cod Fish II inside […]
Read More