The Dredge Report | Week of February 14, 2021

Stage Harbor, Chatham

Sand Shifter – Stage Harbor, Chatham

Dredging continued on Monday, but on Tuesday we had to stop due to the strong northerly winds & seas that lasted throughout the day making dredging dangerous.

On Wednesday we resumed operations but had to stop in the late afternoon to repair a small section of the discharge pipe that cracked.

Dredging resumed early on Thursday morning and continued through Saturday.

A few pictures below taken last Friday afternoon during the snow, sleet and rain conditions.

 

Discharge Pipe

 

Discharge Location near Cockle Cove Beach

Discharge Pump

 

Close up of the Booster Pump – Needed to ‘Boost’ the sand & water another 8,500 feet!

Winter

 

Snow, sleet, rain, snow…a cold, windy Friday afternoon

 

Discharge area

Discharge area near Cockle Cove beach, panoramic view

 

 

Stage Harbor

Project layout – Stage Harbor, Chatham

 

 

 

 